[ARCHIVED] Westmont 2020 Construction Projects

Westmont, Illinois
Date Issued: March 20, 2020

Each year, the Village of Westmont coordinates, schedules, and performs a number of construction updates that improve our community's infrastructure for our residents and businesses.  Also, the County and State perform various construction projects that may impact our community.  It should be noted that weather and other circumstances may impact the schedule of various projects.  Following is a list of scheduled construction projects that will impact the Village of Westmont in the upcoming year.


CBD Alley Reconstruction Project 
Expected completion date: Summer 2020

Location:
Central Business District (CBD) Alley bounded by Cass & Lincoln and Naperville & Norfolk

Description:  
Reconstruction of the deteriorated asphalt alley with decorative pervious brick pavers and pervious concrete base for structural stability.  Project also includes storm sewer installation along the alley.  

Updates:
Construction is scheduled to begin early Spring 2020.


2020 North Washington Watermain Replacement Project
Expected completion date:  Late Summer 2020

Locations:  
Washington Street between Naperville and Burlington

Description:  
Replacement of 2,000 feet of existing deteriorated 6" cast iron watermain with new 8" PVC watermain.  New fire hydrants and services shall be installed along with other related miscellaneous improvements.  

Updates:
Construction is scheduled to begin early Spring 2020.


2020 Gateway Ogden Avenue Beautification Project
Expected completion date: Summer 2020

Locations:  
Median along Ogden Avenue (Route 34) between Pasquinelli and Oakwood
Gateway Sign at Ogden and Pasquinelli
Gateway Sign at Ogden and Cumnor
Gateway Sign at Cass Avenue and 67th Street

Description:  
Installation of a landscape raised median along Ogden Avenue between Pasquinelli Drive and Oakwood Drive.  Landscape median shall include trees, landscaping, sprinkler and electrical system.  New gateway signage shall be installed at 3 locations: Ogden/Pasquinelli, Ogden/Cumnor, and Cass/67th. 

Updates:
Construction is scheduled to begin early Spring 2020.


2018-2019 MFT Street Resurfacing Project
Expected completion date: TBD

Locations:  
Cass Avenue between Ogden and Chicago
Park Street between 55th and Quincy

Description:  
Resurfacing of approximately two (2) miles of roadways at various locations throughout the Village.  Project will include surface grinding, base repairs, curb and gutter repairs, sidewalk repairs and ADA improvements, storm sewer rehab, along with other miscellaneous work.

Updates:
Bid letting for this project has been unsuccessful thus far.  A new bid letting has been scheduled for April 14, 2020.


61st and Richmond Stormwater Detention Modification Project
Expected completion date:  Fall 2020

Location:  
Detention basin located at the northwest corner of 61st Street and Richmond Avenue in the Ashford Subdivision

Description:  
The Village and the Park District are working together to improve the existing detention facility.  Work shall include grading of the basin to provide additional detention volume, correct grading issues to address standing water concerns, upgrade storm sewer pipes within the facility, and provide water quality Best Management Practices (BMP)  to comply with current DuPage County Stormwater Ordinances.  The Village was successful in obtaining over $51k in grant funding from the County's Water Quality Improvement Program (WQIP).

Updates:
The project is currently in design.  More information will follow shortly.


63rd and Richmond Stormwater Detention Modification Project
Expected completion date: Fall 2020

Location:  
Detention basin located at the northwest corner of 63rd Street and Richmond Avenue in the Ashford Subdivision

Description:  
The Village and the Park District are working together to improve the existing detention facility.  Work shall include stabilization of the eroding side slopes, correct failing storm sewer outlets, and provide water quality Best Management Practices (BMP)  to comply with current DuPage County Stormwater Ordinances.  The Village will also install a new Gateway Monument along 63rd Street as part of this project.

Updates:
The project is currently in design.  More information will follow shortly.


Deer Creek Detention Modification Project
Expected completion date: Fall 2020

Location:  
Detention basins located at the north section of Deer Creek Subdivision.

Description:  
The Village and the Park District are working together to improve the existing detention facility.  Work shall include grading of the basin to provide additional detention volume, correct grading issues to address standing water concerns, and provide water quality Best Management Practices (BMP)  to comply with current DuPage County Stormwater Ordinances.  

Updates:
The project is currently in design.  More information shall follow shortly.


For more information regarding Westmont Public Works projects, please contact Mr. Noriel Noriega at 630-981-6295.

 
###

Facebook Twitter Email

Other News in General Press Releases

Call 811 JULIE Before You Dig

Posted on: March 23, 2023

Free Leaf Collection April 10-14

Posted on: February 9, 2023

Village Offices Closed April 7

Posted on: March 14, 2023

2023 Citizens Fire Academy

Posted on: January 10, 2023

2023 No Mow ‘til Mother’s Day

Posted on: December 15, 2022

Chief Riley Recognizes Fire Personnel

Posted on: March 10, 2023

Village Budget Preparation

Posted on: January 20, 2023

METRA Launches metratracker.com

Posted on: January 18, 2023