[ARCHIVED] 2021 Construction Projects

Westmont, Illinois -- Date Issued: May 14, 2021 -*UPDATED May 18,2021

Each year, the Village of Westmont coordinates, schedules, and performs a number of construction updates that improve our community's infrastructure for our residents and businesses. Also, the County and State perform various construction projects that may impact our community. Following is a list of scheduled construction projects that will impact the Village of Westmont in the upcoming year. It should be noted that weather and other circumstances may impact the schedule of various projects.

31st Street Construction Project

While not located in Westmont, the 31st Street road construction project may affect Westmont motorists travelling north of the community.  There will be lane closures on 31st Street from west of Illinois Route 83 to Spring Road.  The project will begin in May and continue through late fall.

Oakmont‌ ‌Lane‌ ‌Water‌ ‌Main‌ ‌Project‌ ‌

Oakmont‌ ‌Lane‌ ‌to‌ ‌Westmont‌ ‌High‌ ‌School‌
Construction‌ ‌of‌ ‌470‌ ‌feet‌ ‌of‌ ‌12”‌ ‌PVC‌ ‌water‌ ‌main.‌ ‌Construction‌ ‌includes‌ ‌water‌ ‌main,‌ ‌one‌ ‌hydrant‌ ‌2‌ ‌valves‌ ‌and‌ ‌other‌ ‌related‌ ‌work.‌
*Target Start Date - May 2021
Target Completion‌ ‌Date‌ ‌- Summer‌ ‌2021‌ ‌

James Addington‌ ‌Plaza‌ ‌Project‌ ‌

West ‌Quincy Street
Completed renovation of train station plaza
*Target Start Date - TBD
Target Completion Date - September 2011 ‌

Water Main Replacement Project

North‌ ‌Washington‌ Street from Burlington‌ ‌Avenue‌ ‌to‌ ‌Naperville‌ ‌Road
Construction‌ ‌of‌ ‌1800‌ ‌feet‌ ‌of‌ ‌8”‌ ‌PVC‌ ‌water‌ ‌main‌ ‌to‌ ‌replace‌ ‌existing‌ ‌6”‌ ‌water‌ ‌main.‌ ‌Construction‌ ‌includes‌ ‌new‌ ‌main,‌ ‌water‌ ‌services,‌ ‌hydrants,‌ ‌valves,‌ ‌and‌ ‌other‌ ‌related‌ ‌work.‌ ‌
*Target Start Date - May 2021
Target Completion‌ ‌Date‌ - ‌Fall‌ ‌2021‌ ‌

East‌ ‌Des‌ ‌Moines‌ ‌Water‌ ‌Main‌ ‌Replacement‌ ‌Project‌ ‌

Linden‌ Avenue ‌to‌ ‌Oak‌ ‌Avenue

Ph2‌ ‌Design‌ ‌Engineering‌ ‌for‌ ‌the‌ ‌construction‌ ‌of‌ ‌3,000‌ ‌feet‌ ‌of‌ ‌8”‌ ‌PVC‌ ‌water‌ ‌main‌ ‌to‌ ‌replace‌ ‌existing‌ ‌6”‌ ‌water‌ ‌main.‌  ‌Construction‌ ‌will‌ ‌include‌ ‌new‌ ‌main,‌ ‌water‌ ‌services,‌ ‌hydrants,‌ ‌valves,‌ ‌and‌ ‌other‌ ‌related‌ ‌work.‌ ‌
*Target Start Date - TBD
Target Completion‌ ‌Date‌ - ‌Fall‌ ‌2021‌ ‌

Water‌ ‌Main‌ ‌Replacement‌ ‌Project‌

E.‌ ‌Dallas‌ Street ‌/‌ ‌S.‌ ‌Linden‌ ‌Avenue /‌ ‌S.‌ ‌Warwick‌ ‌ ‌-‌ ‌DesMoines Street -‌ ‌Richmond‌ Street ‌/‌ ‌Linden‌ ‌Avenue -‌ ‌Warwick‌ ‌Avenue

Ph2‌ ‌Design‌ ‌Engineering‌ ‌for‌ ‌the‌ ‌construction‌ ‌of‌ ‌2,200‌ ‌feet‌ ‌of‌ ‌8”‌ ‌PVC‌ ‌water‌ ‌main‌ ‌to‌ ‌replace‌ ‌existing‌ ‌6”‌ ‌water‌ ‌main.‌  ‌Construction‌ ‌will‌ ‌include‌ ‌new‌ ‌main,‌ ‌water‌ ‌services,‌ ‌hydrants,‌ ‌valves,‌ ‌and‌ ‌other‌ ‌related‌ ‌work.‌ ‌
*Target Start Date - TBD
Target Completion‌ ‌Date‌ - ‌Fall‌ ‌2021‌

Water‌ ‌Main‌ ‌Replacement‌ ‌Project‌

North‌ ‌Warwick‌ ‌from  ‌Burlington‌ Avenue ‌to‌ ‌Chicago‌ ‌Avenue

Ph2‌ ‌Design‌ ‌Engineering‌ ‌for‌ ‌the‌ ‌construction‌ ‌of‌ ‌2,800‌ ‌feet‌ ‌of‌ ‌8”‌ ‌PVC‌ ‌water‌ ‌main‌ ‌to‌ ‌replace‌ ‌existing‌ ‌6”‌ ‌water‌ ‌main.‌  ‌Construction‌ ‌will‌ ‌include‌ ‌new‌ ‌main,‌ ‌water‌ ‌services,‌ ‌hydrants,‌ ‌valves,‌ ‌and‌ ‌other‌ ‌related‌ ‌work.‌ ‌
*Target Start Date - TBD
Target Completion‌ ‌Date‌ - ‌Fall‌ ‌2021‌ ‌

‌Water‌ ‌Main‌ ‌Extension‌ ‌Project‌ ‌

63rd‌ ‌Street‌ from Richmond‌ ‌St‌reet to ‌Western‌ ‌Ave.‌ ‌

Ph2‌ ‌Design‌ ‌Engineering‌ ‌for‌ ‌the‌ ‌construction‌ ‌of‌ ‌2,800‌ ‌feet‌ ‌of‌ ‌8”‌ ‌PVC‌ ‌water‌ ‌main‌ ‌to‌ ‌replace‌ ‌existing‌ ‌6”‌ ‌water‌ ‌main.‌  ‌Construction‌ ‌will‌ ‌include‌ ‌new‌ ‌main,‌ ‌water‌ ‌services,‌ ‌hydrants,‌ ‌valves,‌ ‌and‌ ‌other‌ ‌related‌ ‌work.‌ ‌
*Target Start Date - TBD
Target Completion‌ ‌Date‌ ‌- Fall‌ ‌2021‌ ‌

2021‌ ‌Motor Fuel Tax (MFT‌) ‌Resurfacing‌ ‌Project‌ ‌ ‌

Hot‌ ‌Mix‌ ‌Asphalt‌ ‌resurfacing‌ ‌by‌ ‌pavement‌ ‌grinding,‌ ‌crack‌ ‌control‌ ‌treatment,‌ ‌curb‌ ‌&‌ ‌gutter‌ ‌removal‌ ‌and‌ ‌replacement,‌ ‌sidewalk‌ ‌removal‌ ‌and‌ ‌replacement,‌ ‌binder‌ ‌and‌ ‌surface‌ ‌course,‌ ‌and‌ ‌other‌ ‌related‌ ‌work.‌ ‌
*Target Start Date - TBD
Target Completion‌ ‌Date‌ - ‌Fall‌ ‌2021‌ ‌

Stormwater‌ ‌Project‌ ‌and‌ ‌Gateway‌ ‌Sign

63rd‌ ‌Street‌ ‌and‌ ‌Richmond‌ ‌St.‌

Ph3‌ ‌Design‌ ‌and‌ ‌Construction‌ ‌of‌ ‌the‌ ‌streambank‌ ‌stabilization‌ ‌and‌ ‌native‌ ‌plantings.‌ ‌
*Target Start Date - TBD
Target Completion‌ ‌Date‌ ‌- Fall‌ ‌2021‌

CBD‌ ‌Alley‌ ‌Reconstruction‌ ‌Project‌ ‌(Sec‌ ‌D)

East‌ ‌Alley‌ ‌between‌ ‌Burlington‌ ‌Avenue and‌ ‌Irving‌ ‌Street

Reconstruction‌ ‌of‌ ‌the‌ ‌alley‌ ‌with‌ ‌pervious‌ ‌pavement,‌ ‌installation‌ ‌of‌ ‌new‌ ‌storm‌ ‌sewers‌ ‌and‌ ‌pipe‌ ‌underdrain‌ ‌system‌ ‌and‌ ‌other‌ ‌related‌ ‌work.‌ ‌
*Target Start Date - TBD
Target Completion‌ ‌Date‌ ‌- Fall‌ ‌2021‌ ‌

New‌ ‌Village‌ ‌Fueling‌ ‌Center‌

Westmont Fire Station Headquarters - 6015‌ ‌S.‌ ‌Cass‌ ‌Avenue

Construction‌ ‌of‌ ‌new‌ ‌two 4,000‌ ‌gallon‌ ‌tanks ‌and‌ ‌fueling‌ ‌station‌. ‌ ‌
*Target Start Date - TBD
Target Completion‌ ‌Date‌ - ‌Fall‌ ‌2021‌ ‌

North‌ ‌Water‌ ‌Storage‌ ‌Tower‌ ‌Property‌ ‌Acquisition‌ & Storage Tank Construction

*Behind Westmont High School ‌

Based‌ ‌on‌ ‌the‌ ‌current‌ ‌Village‌ ‌population,‌ ‌IEPA‌ ‌recommends‌ ‌we‌ ‌have‌ ‌a‌ ‌48-hr‌ ‌storage‌ ‌capacity‌ ‌of‌ ‌5.5-million‌ ‌gallons.‌  ‌The‌ ‌Village’s‌ ‌current‌ ‌storage‌ ‌capacity‌ ‌is‌ ‌4.5‌ ‌million‌ ‌gallons.‌  ‌Public‌ ‌Works‌ ‌is‌ ‌seeking‌ ‌funds ‌to‌ ‌secure‌ ‌property‌ ‌on‌ ‌the‌ ‌north‌ ‌side‌ ‌of‌ ‌the‌ ‌Village‌ ‌to‌ ‌construct‌ ‌a‌ ‌1‌ ‌million‌ ‌gallon‌, ‌above‌-ground‌ ‌storage‌ ‌tank.‌ ‌
*Target Start Date - TBD
Completion‌ ‌Date‌ - ‌Spring‌ ‌2022‌ ‌

Stormwater‌ ‌Project‌ ‌

57th‌ ‌St‌reet ‌from Cass‌ ‌Ave‌nue ‌to‌ ‌Adams‌ ‌Street‌

Phase‌ ‌1‌ ‌and‌ ‌Phase‌ ‌2‌ ‌design‌ ‌engineering‌ ‌for‌ ‌the‌ ‌new‌ ‌12”‌ ‌storm‌ ‌sewer.‌ ‌ ‌
*Target Start Date - TBD
Target Completion‌ ‌Date‌ ‌- Spring‌ ‌2022‌ ‌

CBD‌ ‌Alley‌ ‌Reconstruction‌ ‌Project‌ ‌(Sec‌ ‌G)

Alley‌ ‌Between‌ ‌Richmond‌ ‌Avenue ‌and‌ ‌Lincoln‌ ‌Street

Ph2‌ ‌Design‌ ‌Engineering‌ ‌for‌ ‌the‌ ‌reconstruction‌ ‌of‌ ‌the‌ ‌alley‌ ‌with‌ ‌pervious‌ ‌pavement,‌ ‌installation‌ ‌of‌ ‌new‌ storm‌ ‌sewers‌ ‌and‌ ‌pipe‌ ‌underdrain‌ ‌system‌ ‌and‌ ‌other‌ ‌related‌ ‌work.‌ ‌
*Target Start Date - TBD
Target Completion‌ ‌Date‌ ‌- Spring‌ ‌2022‌ ‌

CBD‌ Parking Lot Project

‌Lincoln‌ ‌Street and‌ ‌Irving‌ ‌Street

Construction‌ ‌of‌ ‌the‌ ‌parking‌ ‌Lot‌ ‌and‌ ‌other‌ ‌related‌ ‌work‌. ‌
*Target Start Date - TBD
Target Completion‌ ‌date‌ ‌- Spring‌ ‌2022‌ ‌

Westmont Fire Station Headquarters‌

Parking‌ ‌Lot‌ ‌Expansion‌ ‌Project‌ ‌

Construction‌ ‌of‌ ‌a‌ ‌new‌ ‌parking‌ ‌lot‌.‌  ‌New‌ ‌lot‌ ‌will‌ ‌add‌ ‌approximately‌ ‌24‌ ‌parking‌ ‌spaces‌ ‌and‌ ‌will‌ ‌consist‌ ‌of‌ ‌the‌ ‌new‌ ‌lot,‌ ‌lights,‌ ‌and‌ ‌detention‌ ‌facility‌ ‌modifications.‌ ‌
*Target Start Date - TBD
Target Completion‌ ‌Date‌ ‌- Spring‌ ‌2022‌ ‌

‌Sidewalk‌ ‌Project‌ ‌

Adams‌ ‌Street from 55th‌ ‌Place to ‌Diane‌ ‌Main‌ ‌Park

Ph2‌ ‌Design‌ ‌Engineering‌ ‌for‌ ‌the‌ ‌installation‌ ‌of‌ ‌new‌ ‌public‌ ‌sidewalks‌ ‌on‌ ‌the‌ ‌west‌ ‌side‌ ‌of‌ ‌Adams‌ ‌St..‌
*Target Start Date - TBD
Target Completion‌ ‌Date‌ ‌- Spring‌ ‌2022‌ ‌

For more information regarding infrastructure construction projects in Westmont, contact publicworks@westmont.il.gov.


###


Facebook Twitter Email

Other News in General Press Releases

Call 811 JULIE Before You Dig

Posted on: March 23, 2023

Free Leaf Collection April 10-14

Posted on: February 9, 2023

Village Offices Closed April 7

Posted on: March 14, 2023

2023 Citizens Fire Academy

Posted on: January 10, 2023

2023 No Mow ‘til Mother’s Day

Posted on: December 15, 2022

Chief Riley Recognizes Fire Personnel

Posted on: March 10, 2023

Village Budget Preparation

Posted on: January 20, 2023

METRA Launches metratracker.com

Posted on: January 18, 2023