Date Issued: July 14, 2015
In 2014, the Village approved a street resurfacing plan that will ultimately invest more than $8 million in community road repairs over a 3-year period. The Village is currently in year two of this project.
An independent engineering firm, Infrastructure Management Services, Inc., was contracted in 2012 to perform a Laser Dynaflect study of all roadways in the community to create an initial assessment of road repairs. This study, along with Public Works staff recommendations, was used to create the list of streets to be resurfaced during this project.
The next phase of this project is expected to begin the week of July 20 and continue through the fall. The Village appreciate everyone’s patience while work is being completed.
The roads identified for the 2015 Fall MFT Street Resurfacing Projects include:
* 61ST STREET - Williams Street to Fairview Avenue
* 59TH STREET - Cass Avenue to Cumnor
* LINCOLN STREET - Quincy Street to 55th Street
* WILLIAMS STREET - 63rd Street to Aspen Lane (on 67th Street)
* COVE COURT - Williams Street to West End
* TRACEY COURT - Williams Street to West End
* FALCON PLACE - Cass Avenue to East End
* EAST CASS AVENUE ALLEY - Alley East of Cass Avenue (55th Street to Linden)
For more information regarding Westmont street resurfacing projects, please contact Noriel Noriega at 630-981-6295.